High Voltage
Our client owned an untenanted building and a prospective tenant required an upgrade from 400 Amps to 5000 Amps in order to lease the warehouse. In turn Scarlett Contracting was engaged to liaise with the prospective tenants to determine their requirements and to provide a solution that would see the lease secured.
Scarlett Contracting designed and constructed the electrical infrastructure for Natures Dairy which is a milk processing plant for their required 5000 Amp main switchboard. The MSB incorporated a bus-tie breaker, to accommodate servicing of HV transformers when required, without losing power to the installation, which included: